While the JK BMS-PB Series comes with built-in inverter and parallel communication protocols out of the box, you can still add CANBus and RS485 communication functionality to a Non-PB Series standard board. However, this must be handled during the purchasing phase and cannot be unlocked later via software.
Below is the complete breakdown of how to order, wire, and configure your standard protection board for inverter communication.
1. Crucial Purchase Step: The $10 Customization Requirement
For example: JK-B2A8S20P

Standard Non-PB series boards do not contain the physical hardware or internal routing needed for external communication streams.
The Customization: You must explicitly select the CANBus and RS485 customization option when buying your protection board.
The Cost: This factory modification adds an extra $10 USD to the board’s base price.
The Hardware Lock: For standard boards that were not customized with this feature at the factory, the communication protocol selection area in the app logic is completely blacked out / disabled. Upgrading or changing the board’s firmware will not unlock this feature—it is a permanent hardware limitation.

- If your inverter lacks communication capabilities: it can only control the battery connection—switching it on or off—based on the battery voltage.
2. Identifying the Communication Wire Colors
Once your customized Non-PB board arrives, the communication wiring harness uses specific color-coding to differentiate the signals:

CANBus Communication: The Red and Black wires are designated for the CANBus data lines.
RS485 Communication: The Yellow and White wires are designated for the RS485 data lines.
Purpose: These wires are used to feed real-time battery telemetry data directly into your hybrid inverter for stable, closed-loop system management.
3. Using the Optional

When buying a board customized with CANBus and RS485, you can add an external Interface Board to your order .
Function: This accessory provides standard plug-and-play ports to make connecting your communication lines to the inverter much cleaner and easier.
Option 2

Option 3

- Don’t forget to purchase a display: it not only allows you to check the battery status directly but can also be used to turn the BMS on or off.
4. Multi-Pack Paralleling
If your primary goal is to run multiple battery packs together in parallel, it is highly recommended to purchase the PB Series instead.
The PB series protection boards are specifically designed for expanding battery capacity through parallel connection; using them makes the process more convenient and cost-effective.